Case Study: A180 Brocklesby

Client :
Aone+ Area 12 MAC
Location :
A180 Brocklesby, Stallingborough and Great Coats
Date :
2010 to 2015
Products :
Maxicrete F Thin Bond Concrete Repair (TBR) and Ultraband Fill and Overband

Works on this section of concrete carriageway have been undertaken by Route One over the last five years and have included over 200m2 of Maxicrete F TBR’s and 5000m of Ultraband.

Maxicrete F TBR was been used to repair spalling slabs and pavement cracking up to full depth

Ultraband was used as an alternative to the traditional ‘saw and seal’ method and reduced time, waste and cost. Overall savings were in excess of 30%.

sector-img1
  • BBA/HAPAS approved (Ultraband)
  • Early contractor involvement on installation technique to reduce time, waste and cost
  • Fast curing materials reducing possession times and programme
  • Outputs on Maxicrete F – 10-15m2/Night Shift Outputs on Ultraband – over 1500m/Night Shift
sector-img2

For more information about this and other Route One projects call 01977 799999

"We are pleased by the collaborative approach and flexibility that is a clear foundation of the company."

K Jones

Find out how Route One can help with your project now. Call us on...