Route One were employed by Jackson Civil Engineering to carry out works at Hilton Lane in Telford.

Route One operatives installed a Stirling Lloyd B5 Buried Joint before applying the Stirling Lloyd Eliminator waterproofing system to the deck.

Following resurfacing of the bridge, a crack inducer above the joint was installed.

sector-img1
  • Deck preparation and enclosed shot blasting
  • 900m2 of Eliminator (One coat) installed in 2No shifts
  • Polysulphide joint sealant
  • Associated concrete repairs
  • 12m lin of Sentinel B5 joint installed in 1No shift
sector-img2