Client: AOne+ Area 12 MAC
Location: A180 Stallingborough
Date: February 2011
Products: Maxicrete
Maxicrete thin bond concrete repairs
These works were carried out as part of a larger package of works by Route One which included joint and crack sealing (see Ultra-band case study). Over 100m2 of thin bonded repairs were completed over 2No shifts under road closure.
Maxicrete was used as the material remains flexible meaning there is no requirement to re-cut expansion/contraction joints. Completed repairs can be trafficked within an hour.