Case Study: Lockeridge Bridge

Client :
Balfour Beatty Civil Engineering
Location :
Lockeridge Bridge, Wiltshire
Date :
April 2015
Products :
Eliminator Bridge Deck Waterproofing – Two Coat

Route One carried out waterproofing using Stirling Lloyd’s Eliminator Two Coat System at Lockeridge Bridge.

Route One carried out waterproofing using Stirling Lloyd’s Eliminator Two Coat System at Lockeridge Bridge as part of the refurbishment works.

The works consisted of enclosed shot blasting to the bridge deck before application of the Eliminator waterproofing system. The works were all carried out in one daytime shift.

sector-img1
  • >80m2 deck preparation (enclosed shot blasting)
  • Two coat Eliminator waterproofing and Tack Coat No2
  • Works completed in one day shift
sector-img2

For more information about bridges and structures call 01977 799999

"Very good quality of workmanship."

B Sheldon

Find out how Route One can help with your project now. Call us on...